WJ News

Latest News and Updates from WJ Groundwater and across the Industry.

wj-science-centre-05.jpg

Quick Turnaround Dewatering at Science Centre Station

Being the largest transit expansion in Canada, with significant on-going disruption to Toronto’s population, any delay to the development of Eglinton Crosstown LRT is not welcome news. Especially when that delay is totally unexpected. That’s exactly what happened when the construction crew discovered groundwater where there wasn’t supposed to be any!

Early one morning, WJ Canada received a call for help. The CTS construction team, working at the Science Centre Station, encountered groundwater at the bottom of the excavation. The Science Centre Station is the longest excavation on the entire Eglinton Crosstown project, at 800m in length, with the deepest part being underneath Don Mills Road.

dewatering at Science Centre Station
dewatering at Science Centre Station
dewatering at Science Centre Station

According to a previous hydrogeological investigation, there was not supposed to be water present. Yet, to their surprise, as the CTS crew approached the bottom of an aquifer on a clay Till, they were greeted by approximately 1m of water. This prevented the last section of excavation and concrete placement. It also meant a potentially serious delay to the project!

Once we’d received CTS’s call for help, WJ was on-site within just a few days and we wasted no time in getting straight to work. This involved drilling inclined well-points on both the north and south side of the excavation. We worked from the bottom of the shaft, through the lagging wall, and got the entire system commissioned in record time.

dewatering at Science Centre Station
dewatering at Science Centre Station
dewatering at Science Centre Station

Just two weeks after receiving their call for help, WJ had dewatered the Science Centre Station site. CTS were able to resume excavation in dry conditions. Within 3 months, CTS had completed all concrete and waterproofing systems and WJ was able to decommission the system.

“WJ came in on very short notice and executed a professional and effective dewatering solution. Their solution was cost effective and efficient as the wells were short and installed from the base of the excavation. The solution was tailored to our needs as they allowed us to complete our station build-back all the while remaining functional behind the waterproofing membrane. I would recommend WJ to any contractor in need of a dewatering partner.”

– Diego Ocampo, Project Manager, Science Centre Station

read more
WJ Group AdminQuick Turnaround Dewatering at Science Centre Station
wj-oakwood-07.jpg

Cross Cut Completion at Oakwood Station

The Eglinton Crosstown Light Rail Transit (ECLRT) project consists of 19.7 km of light rail transit running along Eglinton Avenue from Mount Dennis in the west to Kennedy in the east. The project is being designed and constructed by Crosslinx Transit Solutions (CTS).

With such an important and flagship infrastructure project, under constant public scrutiny, given the build disruption to local communities, the stakes were high. CTS needed a true water management partner who would work with them right through to the end.  And that’s where WJ came in.

WJ was called in from the UK to take a look at dewatering requirements of the Eglinton Crosstown Project – a challenging commission, which combines difficult dewatering conditions with innovative construction techniques. Several of the stations within the Eglinton project are being constructed using a unique soil mining technique, known as the New Austrian Tunnelling Method. This meant that our dewatering solutions had to be just as innovative in order to succeed.

Right from the start, the Oakwood main entrance access (called the cross-cut) was flagged as the most challenging aspect of the project. A silty, low-permeability soil matrix that fines towards the bottom of the excavation was located just above a clay interface. Using, wellpoints, ejectors, and deep wells, from the road surface and from confined spaces in TBM tunnels and mined caverns, WJ was able to complete this substantial dewatering feat, without any delay to the CTS mining schedule.

As everyone in mining knows: the mining can never stop!

WJ ensured it never did.

read more
WJ Group AdminCross Cut Completion at Oakwood Station
Farringdon-1.jpg

Crossrail Underground Station at Farringdon

One of several Crossrail projects entrusted to WJ Groundwater, Farringdon Station sits at the heart of London’s transport system and will provide access to three rail networks: Crossrail, London Underground and Network Rail.

read more
WJ Group AdminCrossrail Underground Station at Farringdon
Canary_Crossrail_1.jpg

Crossrail Station, Canary Wharf

Canary Wharf will be one of the largest Crossrail stations. Like the nearby Canary Wharf Tube station, the new Crossrail station has been built in the dock water area, in this case the North Dock of West India Quay.

read more
WJ Group AdminCrossrail Station, Canary Wharf
DSC2072.jpg

HS1 Ashford Tunnels

The HS1 railway between London St Pancras and The Channel Tunnel serves both national and international high-speed routes.

read more
Neil.CoulterHS1 Ashford Tunnels